Action Date | Action Description |
---|---|
Sep 23, 2021 | Maintenance Certification Request |
Sep 28, 2021 | Administrative Review for Completeness |
Sep 29, 2021 | Bio Team Review for Completeness |
Sep 29, 2021 | Application Accepted |
Sep 30, 2021 | Project Manager |
Oct 12, 2021 | Additional Information Requested from Applicant |
Oct 13, 2021 | HPHC Review Pending |
Oct 13, 2021 | HPHC Historical Preservation No Effect |
Mar 09, 2022 | Additional Information Received |
Apr 08, 2022 | Biologist Report |
Apr 14, 2022 | Permit Approved |
Apr 14, 2022 | Typist for Processing |
Apr 14, 2022 | Executive Sign Off |
Apr 14, 2022 | Sent to Photo Copy |
Apr 19, 2022 | Permit Mailed |
May 25, 2022 | Land Evidence Date |
Oct 18, 2023 | Monitoring Report |