Action Date | Action Description |
---|---|
Sep 24, 2021 | Buffer Zone Management Application Received |
Sep 28, 2021 | Administrative Review for Completeness |
Oct 05, 2021 | Bio Team Review for Completeness |
Oct 13, 2021 | Additional Information Requested from Applicant |
Oct 25, 2021 | Additional Information Received |
Oct 26, 2021 | Bio Team Review for Completeness |
Oct 26, 2021 | Application Accepted |
Oct 26, 2021 | Project Manager |
Nov 05, 2021 | HPHC Review Pending |
Nov 05, 2021 | HPHC Historical Preservation No Effect |
Nov 08, 2021 | Biologist Report |
Nov 09, 2021 | Typist for Processing |
Nov 09, 2021 | Executive Sign Off |
Nov 09, 2021 | Sent to Photo Copy |
Nov 09, 2021 | Permit Approved |
Nov 15, 2021 | Permit Mailed |
Nov 24, 2021 | Land Evidence Date |