Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Sep 27, 2021 | Assent Application Received |
Sep 30, 2021 | Administrative Review for Completeness |
Oct 05, 2021 | Bio Team Review for Completeness |
Oct 05, 2021 | Application Accepted |
Oct 05, 2021 | Project Manager |
Oct 05, 2021 | Category B assigned |
Oct 20, 2021 | 30 day Public Notice Issued |
Nov 20, 2021 | Public Notice End Date |
Feb 03, 2022 | Typist for Processing |
Feb 03, 2022 | Biologist Report |
Feb 03, 2022 | Executive Sign Off |
Feb 03, 2022 | Sent to Photo Copy |
Feb 03, 2022 | Engineering Report |
Feb 03, 2022 | Permit Approved |
Feb 07, 2022 | Permit Mailed |
Feb 21, 2022 | Land Evidence Date |