Action Date | Action Description |
---|---|
Oct 21, 2021 | Preliminary Determination Request (Coastal) |
Oct 25, 2021 | Administrative Review for Completeness |
Nov 04, 2021 | Bio Team Review for Completeness |
Nov 04, 2021 | Application Accepted |
Nov 04, 2021 | Project Manager |
Nov 08, 2021 | Biologist Report |
Nov 09, 2021 | Typist for Processing |
Nov 09, 2021 | Executive Sign Off |
Nov 09, 2021 | Sent to Photo Copy |
Nov 09, 2021 | Within CRMC Jurisdiction |
Nov 22, 2021 | HPHC Historical Preservation Comments/Concerns |
Dec 06, 2021 | Correspondence Received |
Dec 06, 2021 | Correspondence Mailed/Faxed/E-mailed |