Action Date | Action Description |
---|---|
HPHC Review Pending | |
Nov 01, 2021 | Assent Application Received |
Nov 03, 2021 | Administrative Review for Completeness |
Nov 09, 2021 | Bio Team Review for Completeness |
Nov 09, 2021 | Application Accepted |
Nov 09, 2021 | Project Manager |
Nov 09, 2021 | Category A* (Docks) |
Nov 17, 2021 | HPHC Review Pending |
Nov 17, 2021 | HPHC Historical Preservation No Effect |
Dec 06, 2021 | 30 day Public Notice Issued |
Jan 06, 2022 | Public Notice End Date |
May 06, 2022 | Dock Meeting Scheduled (Admin) |
Jun 08, 2022 | US Army Corps of Engineers Approval Received |
Sep 14, 2022 | Plans Received |
Jan 26, 2023 | Typist for Processing |
Jan 26, 2023 | Executive Sign Off |
Jan 26, 2023 | Sent to Photo Copy |
Jan 26, 2023 | Permit Approved |
Jan 26, 2023 | Engineering Report |
Jan 27, 2023 | Permit Mailed |
Feb 08, 2023 | Land Evidence Date |
Feb 15, 2023 | Commencement of Work Notice received |
Aug 21, 2023 | Modification Request |
Aug 21, 2023 | Dock Post-Construction Certification by Engineer received. |
Aug 25, 2023 | Administrative Review for Completeness |
Sep 11, 2023 | Bio Team Review for Completeness |
Sep 11, 2023 | Project Manager |
Sep 13, 2023 | 30 day Public Notice Issued |
Oct 13, 2023 | Public Notice End Date |
Dec 04, 2023 | Plans Received |
Dec 04, 2023 | Biologist Report |
Dec 08, 2023 | Modification Approved |
Dec 13, 2023 | Permit Mailed |
Apr 05, 2024 | Land Evidence Date |