Action Date | Action Description |
---|---|
HPHC Review Pending | |
Engineering Report | |
Nov 12, 2021 | Assent Application Received |
Nov 15, 2021 | Administrative Review for Completeness |
Dec 02, 2021 | Eng Team Review for Completeness |
Dec 02, 2021 | Deficient Application - Owner Notification Sent |
Mar 01, 2024 | Deficiency Response Received |
Mar 12, 2024 | Eng Team Review for Completeness |
Mar 12, 2024 | Application Accepted |
Mar 12, 2024 | Project Manager |
Apr 12, 2024 | 30 day Public Notice Issued |
May 10, 2024 | 1.1.6 Meeting - tabled |
May 12, 2024 | Public Notice End Date |
Jul 10, 2024 | Dock Subcommittee Meeting Held |
Jul 17, 2024 | Additional Information Requested from Applicant |