Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Nov 19, 2021 | Assent Application Received |
Nov 24, 2021 | Administrative Review for Completeness |
Nov 24, 2021 | Category A* (Docks) |
Feb 07, 2022 | Deficient Application - Owner Notification Sent |
Feb 07, 2022 | Bio Team Review for Completeness |
Feb 25, 2022 | Deficiency Response Received |
Feb 28, 2022 | Plans Received |
Mar 10, 2022 | Bio Team Review for Completeness |
Mar 10, 2022 | Application Accepted |
Mar 10, 2022 | Project Manager |
Mar 10, 2022 | Category A* (Docks) |
Mar 21, 2022 | HPHC Historical Preservation No Effect |
Mar 21, 2022 | HPHC Review Pending |
Mar 24, 2022 | 30 day Public Notice Issued |
Apr 24, 2022 | Public Notice End Date |
May 13, 2022 | US Army Corps of Engineers Approval Received |
Jun 20, 2022 | Dock/1.1.6 Review approval |
Jul 07, 2022 | Correspondence Mailed/Faxed/E-mailed |
Jul 08, 2022 | Plans Received |
Jul 26, 2022 | Biologist Report |
Aug 01, 2022 | Typist for Processing |
Aug 01, 2022 | Executive Sign Off |
Aug 01, 2022 | Permit Approved |
Aug 01, 2022 | Permit Mailed |
Jan 10, 2023 | Land Evidence Date |