Action Date | Action Description |
---|---|
Nov 29, 2021 | Assent Application Received |
Nov 30, 2021 | Administrative Review for Completeness |
Dec 16, 2021 | Bio Team Review for Completeness |
Dec 16, 2021 | Application Accepted |
Dec 16, 2021 | Project Manager |
Jan 13, 2022 | HPHC Historical Preservation No Effect |
Jan 13, 2022 | HPHC Review Pending |
Jan 20, 2022 | Biologist Report |
Jan 25, 2022 | Typist for Processing |
Jan 25, 2022 | Executive Sign Off |
Jan 25, 2022 | Sent to Photo Copy |
Jan 25, 2022 | Permit Approved |
Jan 27, 2022 | Permit Mailed |
Aug 09, 2022 | Land Evidence Date |