Action Date | Action Description |
---|---|
Dec 06, 2021 | Maintenance Certification Request |
Dec 10, 2021 | Administrative Review for Completeness |
Dec 14, 2021 | Eng Team Review for Completeness |
Dec 14, 2021 | Application Accepted |
Dec 15, 2021 | Project Manager |
Jan 12, 2022 | Engineering Report |
Jan 24, 2022 | Permit Approved |
Jan 24, 2022 | Permit Mailed |
Feb 25, 2022 | HPHC Historical Preservation No Effect |
Feb 25, 2022 | HPHC Review Pending |