Action Date | Action Description |
---|---|
Dec 14, 2021 | Assent Application Received |
Dec 17, 2021 | Administrative Review for Completeness |
Dec 17, 2021 | CHA Worksheet received |
Jan 05, 2022 | Bio Team Review for Completeness |
Jan 05, 2022 | Application Accepted |
Jan 05, 2022 | Project Manager |
Jan 10, 2022 | Plans Received |
Feb 07, 2022 | HPHC Historical Preservation No Effect |
Feb 07, 2022 | HPHC Review Pending |
May 05, 2022 | Additional Information Received |
May 12, 2022 | Biologist Report |
May 13, 2022 | Typist for Processing |
May 13, 2022 | Permit Approved |
May 16, 2022 | Permit Mailed |
May 16, 2022 | Executive Sign Off |
May 16, 2022 | Sent to Photo Copy |
Aug 15, 2022 | Land Evidence Date |