Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Jan 04, 2022 | Assent Application Received |
Jan 06, 2022 | Administrative Review for Completeness |
Jan 28, 2022 | Category B assigned |
Jan 28, 2022 | Bio Team Review for Completeness |
Jan 28, 2022 | Application Accepted |
Jan 28, 2022 | Project Manager |
Feb 04, 2022 | 30 day Public Notice Issued |
Feb 07, 2022 | HPHC Review Pending |
Feb 07, 2022 | HPHC Historical Preservation No Effect |
Mar 04, 2022 | Public Notice End Date |
Jun 08, 2022 | US Army Corps of Engineers Approval Received |
Jul 18, 2022 | Biologist Report |
Jul 18, 2022 | Engineering Report |
Jul 21, 2022 | Typist for Processing |
Jul 21, 2022 | Permit Approved |
Jul 25, 2022 | Permit Mailed |
Jul 28, 2022 | Land Evidence Date |