Action Date | Action Description |
---|---|
Jan 28, 2022 | Assent Application Received |
Feb 01, 2022 | Administrative Review for Completeness |
Feb 14, 2022 | Bio Team Review for Completeness |
Feb 14, 2022 | Application Accepted |
Feb 14, 2022 | Project Manager |
Feb 24, 2022 | Additional Information Requested from Applicant |
Feb 25, 2022 | HPHC Historical Preservation No Effect |
Feb 25, 2022 | HPHC Review Pending |
Mar 24, 2022 | Note to File |
May 18, 2022 | Additional Information Received |
May 23, 2022 | 30 day Public Notice Issued |
Jun 23, 2022 | Public Notice End Date |
Sep 13, 2022 | Engineering Report |
Sep 16, 2022 | Permit Mailed |
Sep 16, 2022 | Typist for Processing |
Sep 16, 2022 | Executive Sign Off |
Sep 16, 2022 | Sent to Photo Copy |
Sep 16, 2022 | Permit Approved |
Oct 31, 2022 | Land Evidence Date |