Action Date | Action Description |
---|---|
Feb 01, 2022 | Assent Application Received |
Feb 02, 2022 | Administrative Review for Completeness |
Feb 04, 2022 | Bio Team Review for Completeness |
Feb 04, 2022 | Deficient Application - Owner Notification Sent |
Feb 18, 2022 | Deficiency Response Received |
Feb 21, 2022 | Bio Team Review for Completeness |
Feb 21, 2022 | Application Accepted |
Feb 24, 2022 | Project Manager |
Mar 04, 2022 | HPHC Review Pending |
Mar 04, 2022 | HPHC Historical Preservation No Effect |
Mar 23, 2022 | Typist for Processing |
Mar 23, 2022 | Executive Sign Off |
Mar 23, 2022 | Sent to Photo Copy |
Mar 23, 2022 | Biologist Report |
Mar 23, 2022 | Permit Approved |
Mar 29, 2022 | Permit Mailed |
Apr 18, 2022 | Land Evidence Date |