Action Date | Action Description |
---|---|
Feb 17, 2022 | Assent Application Received |
Feb 22, 2022 | Administrative Review for Completeness |
Feb 23, 2022 | Eng Team Review for Completeness |
Feb 23, 2022 | Application Accepted |
Feb 24, 2022 | Project Manager |
Feb 24, 2022 | CHA Worksheet received |
Mar 03, 2022 | 30 day Public Notice Issued |
Mar 21, 2022 | HPHC Historical Preservation No Effect |
Apr 03, 2022 | Public Notice End Date |
Apr 18, 2022 | Public Notice End Date Extension Granted |
Apr 25, 2022 | Comments Received |
Apr 26, 2022 | Engineering Report |
Apr 29, 2022 | Typist for Processing |
Apr 29, 2022 | Executive Sign Off |
Apr 29, 2022 | Sent to Photo Copy |
Apr 29, 2022 | Permit Approved |
May 02, 2022 | Permit Mailed |
May 06, 2022 | Land Evidence Date |