Action Date | Action Description |
---|---|
Feb 25, 2022 | Assent Application Received |
Mar 04, 2022 | Administrative Review for Completeness |
Mar 07, 2022 | Eng Team Review for Completeness |
Mar 07, 2022 | Application Accepted |
Mar 07, 2022 | Project Manager |
Mar 30, 2022 | HPHC Historical Preservation Comments/Concerns |
Mar 30, 2022 | HPHC Review Pending |
Apr 28, 2022 | HPHC Historical Preservation No Effect |
May 05, 2022 | Engineering Report |
May 06, 2022 | Typist for Processing |
May 09, 2022 | Executive Sign Off |
May 09, 2022 | Sent to Photo Copy |
May 09, 2022 | Permit Approved |
May 09, 2022 | Permit Mailed |
May 13, 2022 | Land Evidence Date |
Jul 27, 2023 | Modification Request |
Jul 31, 2023 | Administrative Review for Completeness |
Aug 16, 2023 | Eng Team Review for Completeness |
Aug 17, 2023 | Application Accepted |
Aug 17, 2023 | Project Manager |
Sep 22, 2023 | HPHC Historical Preservation No Effect |
Sep 27, 2023 | Engineering Report |
Oct 03, 2023 | Typist for Processing |
Oct 03, 2023 | Executive Sign Off |
Oct 03, 2023 | Sent to Photo Copy |
Oct 03, 2023 | Modification Approved |
Oct 05, 2023 | Permit Mailed |
Oct 12, 2023 | Land Evidence Date |