Action Date | Action Description |
---|---|
Mar 22, 2022 | Maintenance Certification Request |
Mar 25, 2022 | Administrative Review for Completeness |
Apr 04, 2022 | Eng Team Review for Completeness |
Apr 04, 2022 | Eng Team Review for Completeness |
Apr 04, 2022 | Deficient Application - Owner Notification Sent |
Dec 12, 2022 | Deficiency Response Received |
Jan 04, 2023 | Eng Team Review for Completeness |
Jan 04, 2023 | Application Accepted |
Jan 04, 2023 | Project Manager |
Jan 24, 2023 | Plans Received |
Jan 25, 2023 | Engineering Report |
Jan 27, 2023 | HPHC Historical Preservation No Effect |
Feb 09, 2023 | Typist for Processing |
Feb 09, 2023 | Executive Sign Off |
Feb 09, 2023 | Sent to Photo Copy |
Feb 09, 2023 | Permit Approved |
Feb 13, 2023 | Permit Mailed |
Mar 14, 2023 | Land Evidence Date |