Action Date | Action Description |
---|---|
Mar 28, 2022 | Buffer Zone Management Application Received |
Apr 01, 2022 | Administrative Review for Completeness |
Apr 04, 2022 | Bio Team Review for Completeness |
Apr 04, 2022 | Application Accepted |
Apr 04, 2022 | Project Manager |
Apr 11, 2022 | HPHC Review Pending |
Apr 11, 2022 | HPHC Historical Preservation No Effect |
Apr 21, 2022 | Additional Information Requested from Applicant |
Mar 02, 2023 | Plans Received |
Mar 03, 2023 | Biologist Report |
Mar 23, 2023 | Typist for Processing |
Mar 23, 2023 | Executive Sign Off |
Mar 23, 2023 | Sent to Photo Copy |
Mar 23, 2023 | Permit Approved |
Mar 28, 2023 | Permit Mailed |
Apr 21, 2023 | Land Evidence Date |