Action Date | Action Description |
---|---|
Apr 04, 2022 | CHA Worksheet received |
Apr 04, 2022 | Assent Application Received |
Apr 08, 2022 | Administrative Review for Completeness |
Apr 25, 2022 | Bio Team Review for Completeness |
Apr 25, 2022 | Application Accepted |
Apr 25, 2022 | Project Manager |
Jun 16, 2022 | Biologist Report |
Jun 16, 2022 | HPHC Historical Preservation No Effect |
Jun 16, 2022 | Typist for Processing |
Jun 16, 2022 | Executive Sign Off |
Jun 16, 2022 | Sent to Photo Copy |
Jun 16, 2022 | Permit Approved |
Jun 16, 2022 | HPHC Review Pending |
Jun 16, 2022 | Permit Mailed |
Jul 15, 2022 | Land Evidence Date |
Jul 18, 2022 | Commencement of Work Notice received |