Action Date | Action Description |
---|---|
Monitoring Report | |
Apr 20, 2022 | Buffer Zone Management Application Received |
Apr 26, 2022 | Administrative Review for Completeness |
May 04, 2022 | Deficient Application - Owner Notification Sent |
Jun 02, 2022 | Deficient Application Picked Up |
Jun 02, 2022 | Bio Team Review for Completeness |
Sep 06, 2023 | Deficiency Response Received |
Sep 20, 2023 | Bio Team Review for Completeness |
Sep 20, 2023 | Deficient Application - Owner Notification Sent |
Nov 09, 2023 | Deficiency Response Received |
Nov 20, 2023 | Bio Team Review for Completeness |
Nov 20, 2023 | Application Accepted |
Nov 20, 2023 | Project Manager |
Dec 01, 2023 | HPHC Historical Preservation No Effect |
Jan 03, 2024 | Biologist Report |
Jan 05, 2024 | Typist for Processing |
Jan 05, 2024 | Executive Sign Off |
Jan 05, 2024 | Sent to Photo Copy |
Jan 05, 2024 | Permit Approved |
Jan 09, 2024 | Permit Mailed |
Feb 08, 2024 | Land Evidence Date |