Action Date | Action Description |
---|---|
May 10, 2022 | Assent Application Received |
May 13, 2022 | Administrative Review for Completeness |
May 24, 2022 | Eng Team Review for Completeness |
May 24, 2022 | Application Accepted |
May 25, 2022 | Project Manager |
Jun 02, 2022 | HPHC Review Pending |
Jun 02, 2022 | HPHC Historical Preservation No Effect |
Jun 07, 2022 | 30 day Public Notice Issued |
Jun 21, 2022 | Comments Received |
Jul 07, 2022 | Public Notice End Date |
Jan 26, 2023 | Engineering Report |
Jan 30, 2023 | Typist for Processing |
Jan 30, 2023 | Executive Sign Off |
Jan 30, 2023 | Sent to Photo Copy |
Jan 30, 2023 | Permit Approved |
Feb 07, 2023 | Permit Mailed |
Feb 21, 2023 | Land Evidence Date |