Action Date | Action Description |
---|---|
May 13, 2022 | Assent Application Received |
May 20, 2022 | Administrative Review for Completeness |
Jun 01, 2022 | Bio Team Review for Completeness |
Jun 01, 2022 | Application Accepted |
Jun 06, 2022 | Project Manager |
Jun 22, 2022 | HPHC Historical Preservation No Effect |
Jun 22, 2022 | HPHC Review Pending |
Jul 28, 2022 | Biologist Report |
Aug 04, 2022 | Typist for Processing |
Aug 04, 2022 | Executive Sign Off |
Aug 04, 2022 | Sent to Photo Copy |
Aug 04, 2022 | Permit Approved |
Aug 04, 2022 | Permit Mailed |
Sep 13, 2022 | Commencement of Work Notice received |
Oct 17, 2023 | Land Evidence Date |