Action Date | Action Description |
---|---|
Jun 01, 2022 | Assent Application Received |
Jun 07, 2022 | Administrative Review for Completeness |
Jun 21, 2022 | Eng Team Review for Completeness |
Jun 21, 2022 | Application Accepted |
Jun 21, 2022 | Project Manager |
Jul 22, 2022 | HPHC Review Pending |
Jul 22, 2022 | HPHC Historical Preservation No Effect |
Sep 27, 2022 | 30 day Public Notice Issued |
Oct 20, 2022 | Letter of Support for Project |
Oct 27, 2022 | Public Notice End Date |
Nov 10, 2022 | Correspondence Received |
Nov 23, 2022 | Engineering Report |
Nov 28, 2022 | Executive Signoff of Staff Reports |
Nov 29, 2022 | Ready to Schedule Semi-Monthly Meeting |
Dec 27, 2022 | Mail Agenda Notice |
Jan 10, 2023 | Semi-Monthly Meeting Date Scheduled |
Feb 20, 2023 | Entry of Appearance Received |
Feb 22, 2023 | Stipulation Package by Engineer |
Mar 01, 2023 | Legal Response/Decision |
Mar 29, 2023 | Typist for Processing |
Mar 30, 2023 | Executive Sign Off |
Mar 30, 2023 | Permit Approved |
Mar 31, 2023 | Permit Mailed |
Apr 04, 2023 | Commencement of Work Notice received |
Apr 07, 2023 | Land Evidence Date |