Action Date | Action Description |
---|---|
Jun 01, 2022 | Assent Application Received |
Jun 01, 2022 | CHA Worksheet received |
Jun 07, 2022 | Administrative Review for Completeness |
Jun 23, 2022 | Bio Team Review for Completeness |
Jun 23, 2022 | Application Accepted |
Jun 23, 2022 | Project Manager |
Jun 24, 2022 | Plans Received |
Jun 28, 2022 | Biologist Report |
Jul 22, 2022 | HPHC Historical Preservation No Effect |
Jul 22, 2022 | HPHC Review Pending |
Jul 26, 2022 | Permit Mailed |
Jul 26, 2022 | Typist for Processing |
Jul 26, 2022 | Executive Sign Off |
Jul 26, 2022 | Sent to Photo Copy |
Jul 26, 2022 | Permit Approved |
Jan 26, 2023 | Land Evidence Date |