Action Date | Action Description |
---|---|
Legal Response/Decision | |
Land Evidence Date | |
Jun 16, 2022 | Assent Application Received |
Jun 20, 2022 | Administrative Review for Completeness |
Jun 23, 2022 | Eng Team Review for Completeness |
Jun 23, 2022 | Application Accepted |
Jun 28, 2022 | Project Manager |
Jul 28, 2022 | 30 day Public Notice Issued |
Aug 25, 2022 | Comments Received |
Aug 28, 2022 | Public Notice End Date |
Dec 01, 2022 | HPHC Historical Preservation No Effect |
Jan 11, 2023 | Additional Information Received |
Feb 20, 2023 | Plans Received |
Feb 20, 2023 | Engineering Report |
Mar 16, 2023 | Mail Agenda Notice |
Mar 28, 2023 | Continued application |
Mar 28, 2023 | Semi-Monthly Meeting Date Scheduled |
Apr 04, 2023 | Mail Agenda Notice |
Apr 24, 2023 | Council Approval Granted |
Apr 24, 2023 | Semi-Monthly Meeting Date Scheduled |
Oct 15, 2024 | Stipulation Package by Engineer |
Oct 18, 2024 | Typist for Processing |
Oct 18, 2024 | Executive Sign Off |
Oct 18, 2024 | Sent to Photo Copy |
Oct 18, 2024 | Permit Approved |
Oct 21, 2024 | Permit Mailed |