Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Engineering Report | |
Aug 19, 2022 | Assent Application Received |
Aug 22, 2022 | Administrative Review for Completeness |
Aug 23, 2022 | Eng Team Review for Completeness |
Aug 23, 2022 | Application Accepted |
Aug 24, 2022 | Project Manager |
Aug 24, 2022 | Category A* (Docks) |
Sep 21, 2022 | HPHC Historical Preservation No Effect |
Oct 05, 2022 | US Army Corps of Engineers Approval Received |
Oct 22, 2022 | Public Notice End Date |
Jan 11, 2023 | Typist for Processing |
Jan 11, 2023 | Executive Sign Off |
Jan 11, 2023 | Sent to Photo Copy |
Jan 11, 2023 | Permit Approved |
Jan 11, 2023 | Engineering Report |
Jan 13, 2023 | Permit Mailed |
Jan 27, 2023 | Land Evidence Date |
Dec 04, 2023 | Modification Request |
Dec 05, 2023 | Administrative Review for Completeness |
Dec 13, 2023 | Eng Team Review for Completeness |
Dec 13, 2023 | Project Manager |
Dec 13, 2023 | Application Accepted |
Jan 17, 2024 | HPHC Historical Preservation No Effect |
May 20, 2024 | Additional Information Received |
Aug 22, 2024 | Additional Information Received |
Sep 05, 2024 | 30 day Public Notice Issued |
Sep 16, 2024 | Objections/Comments Received |
Oct 05, 2024 | Public Notice End Date |
Oct 29, 2024 | Correspondence Received |