Action Date | Action Description |
---|---|
Sep 01, 2022 | Assent Application Received |
Sep 09, 2022 | Administrative Review for Completeness |
Sep 14, 2022 | Bio Team Review for Completeness |
Sep 14, 2022 | Application Accepted |
Sep 20, 2022 | Project Manager |
Oct 24, 2022 | Additional Information Received |
Oct 27, 2022 | 30 day Public Notice Issued |
Nov 10, 2022 | HPHC Historical Preservation No Effect |
Nov 21, 2022 | Correspondence Received |
Nov 27, 2022 | Public Notice End Date |
Nov 29, 2022 | Plans Received |
Dec 07, 2022 | Comments Received |
Dec 19, 2022 | Public Notice End Date Extension Granted |
Apr 14, 2023 | Objections/Comments Received |
Apr 19, 2023 | Correspondence Received |
Apr 20, 2023 | Entry of Appearance Received |
May 01, 2023 | Mail Agenda Notice |
May 02, 2023 | Executive Signoff of Staff Reports |
May 02, 2023 | Engineering Report |
May 09, 2023 | Semi-Monthly Meeting Date Scheduled |
May 09, 2023 | Council Approval Granted |
Aug 16, 2023 | Legal Response/Decision |
Sep 15, 2023 | Stipulation Package by Engineer |
Sep 27, 2023 | Permit Mailed |
Sep 27, 2023 | Typist for Processing |
Sep 27, 2023 | Executive Sign Off |
Sep 27, 2023 | Sent to Photo Copy |
Sep 27, 2023 | Permit Approved |
Oct 11, 2023 | Land Evidence Date |