Action Date | Action Description |
---|---|
Sep 21, 2022 | Assent Application Received |
Sep 26, 2022 | Administrative Review for Completeness |
Sep 30, 2022 | Bio Team Review for Completeness |
Sep 30, 2022 | Application Accepted |
Oct 05, 2022 | Project Manager |
Oct 05, 2022 | Category A* (Docks) |
Oct 06, 2022 | 30 day Public Notice Issued |
Oct 07, 2022 | HPHC Historical Preservation No Effect |
Nov 05, 2022 | Public Notice End Date |
Nov 21, 2022 | Dock/1.1.6 Review approval |
Nov 22, 2022 | Biologist Report |
Dec 28, 2022 | Typist for Processing |
Jan 03, 2023 | Executive Sign Off |
Jan 03, 2023 | Sent to Photo Copy |
Jan 03, 2023 | Permit Approved |
Jan 04, 2023 | Permit Mailed |
Feb 07, 2023 | Land Evidence Date |
Dec 08, 2023 | Dock Post-Construction Certification by Engineer received. |