Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Nov 18, 2022 | Assent Application Received |
Nov 22, 2022 | Administrative Review for Completeness |
Nov 23, 2022 | Bio Team Review for Completeness |
Nov 23, 2022 | Application Accepted |
Nov 30, 2022 | Project Manager |
Nov 30, 2022 | Category A* (Docks) |
Nov 30, 2022 | 30 day Public Notice Issued |
Dec 20, 2022 | HPHC Historical Preservation No Effect |
Dec 28, 2022 | Comments Received |
Dec 30, 2022 | Comments Received |
Dec 30, 2022 | Public Notice End Date |
Jan 25, 2023 | Biologist Report |
Feb 06, 2023 | Typist for Processing |
Feb 06, 2023 | Executive Sign Off |
Feb 06, 2023 | Sent to Photo Copy |
Feb 06, 2023 | Permit Approved |
Feb 13, 2023 | Permit Mailed |
Oct 16, 2023 | Land Evidence Date |