Action Date | Action Description |
---|---|
Nov 22, 2022 | Assent Application Received |
Nov 29, 2022 | Administrative Review for Completeness |
Nov 30, 2022 | Bio Team Review for Completeness |
Nov 30, 2022 | Application Accepted |
Dec 02, 2022 | Project Manager |
Dec 21, 2022 | Plans Received |
Jan 11, 2023 | HPHC Historical Preservation No Effect |
Feb 03, 2023 | Biologist Report |
Feb 15, 2023 | Typist for Processing |
Feb 15, 2023 | Executive Sign Off |
Feb 15, 2023 | Sent to Photo Copy |
Feb 15, 2023 | Permit Approved |
Feb 16, 2023 | Permit Mailed |
Mar 20, 2023 | Land Evidence Date |