Action Date | Action Description |
---|---|
Jan 10, 2023 | CHA Worksheet received |
Jan 10, 2023 | Assent Application Received |
Jan 17, 2023 | Administrative Review for Completeness |
Feb 08, 2023 | Eng Team Review for Completeness |
Feb 08, 2023 | Project Manager |
Feb 08, 2023 | Application Accepted |
Mar 10, 2023 | HPHC Historical Preservation Comments/Concerns |
Mar 21, 2023 | Additional Information Received |
Apr 26, 2023 | Additional Information Received |
May 16, 2023 | 30 day Public Notice Issued |
Jun 13, 2023 | Comments Received |
Jun 16, 2023 | Public Notice End Date |
Aug 01, 2023 | Dock/1.1.6 Review approval |
Sep 11, 2023 | HPHC Historical Preservation No Effect |
Sep 20, 2023 | Engineering Report |
Sep 22, 2023 | Permit Approved |
Sep 22, 2023 | Typist for Processing |
Sep 22, 2023 | Executive Sign Off |
Sep 22, 2023 | Sent to Photo Copy |
Sep 25, 2023 | Permit Mailed |
Oct 03, 2023 | Land Evidence Date |