Action Date | Action Description |
---|---|
Mar 01, 2023 | Maintenance Certification Request |
Mar 07, 2023 | Administrative Review for Completeness |
Mar 10, 2023 | Eng Team Review for Completeness |
Mar 10, 2023 | Application Accepted |
Mar 10, 2023 | Project Manager |
Mar 21, 2023 | Engineering Report |
Apr 04, 2023 | Typist for Processing |
Apr 04, 2023 | Executive Sign Off |
Apr 04, 2023 | Sent to Photo Copy |
Apr 04, 2023 | Permit Approved |
Apr 06, 2023 | Permit Mailed |
Apr 07, 2023 | HPHC Historical Preservation No Effect |