Action Date | Action Description |
---|---|
Land Evidence Date | |
Mar 02, 2023 | Maintenance Certification Request |
Mar 08, 2023 | Administrative Review for Completeness |
Mar 10, 2023 | Application Accepted |
Mar 10, 2023 | Project Manager |
Mar 10, 2023 | Bio Team Review for Completeness |
Mar 17, 2023 | Biologist Report |
Mar 22, 2023 | HPHC Historical Preservation No Effect |
Mar 23, 2023 | Typist for Processing |
Mar 23, 2023 | Executive Sign Off |
Mar 23, 2023 | Sent to Photo Copy |
Mar 23, 2023 | Permit Approved |
Mar 28, 2023 | Permit Mailed |