Action Date | Action Description |
---|---|
US Army Corps of Engineers Approval Required | |
Mar 07, 2023 | CHA Worksheet received |
Mar 07, 2023 | Assent Application Received |
Mar 09, 2023 | Administrative Review for Completeness |
Mar 20, 2023 | Additional Information Received |
Mar 22, 2023 | Eng Team Review for Completeness |
Mar 22, 2023 | Bio Team Review for Completeness |
Mar 22, 2023 | Project Manager |
Mar 22, 2023 | Application Accepted |
Mar 22, 2023 | CHA Worksheet received |
Mar 27, 2023 | HPHC Historical Preservation No Effect |
Jul 17, 2023 | Plans Received |
Aug 15, 2023 | 30 day Public Notice Issued |
Sep 15, 2023 | Public Notice End Date |
Oct 31, 2023 | Typist for Processing |
Oct 31, 2023 | Executive Sign Off |
Oct 31, 2023 | Sent to Photo Copy |
Oct 31, 2023 | Permit Approved |
Oct 31, 2023 | Engineering Report |
Nov 03, 2023 | Permit Mailed |
Dec 05, 2023 | Land Evidence Date |