Action Date | Action Description |
---|---|
Assent Requirement | |
Apr 05, 2023 | Buffer Zone Management Application Received |
Apr 06, 2023 | Administrative Review for Completeness |
Apr 12, 2023 | Bio Team Review for Completeness |
Apr 19, 2023 | Deficient Application - Owner Notification Sent |
Aug 08, 2023 | Deficiency Response Received |
Aug 28, 2023 | Bio Team Review for Completeness |
Aug 28, 2023 | Project Manager |
Sep 22, 2023 | Biologist Report |
Sep 22, 2023 | Application Accepted |
Sep 25, 2023 | Typist for Processing |
Sep 25, 2023 | Executive Sign Off |
Sep 25, 2023 | Sent to Photo Copy |
Sep 25, 2023 | Permit Approved |
Sep 26, 2023 | Permit Mailed |
Oct 02, 2023 | Land Evidence Date |