Action Date | Action Description |
---|---|
Apr 07, 2023 | Assent Application Received |
Apr 17, 2023 | Administrative Review for Completeness |
Apr 21, 2023 | Eng Team Review for Completeness |
Apr 21, 2023 | Bio Team Review for Completeness |
Apr 21, 2023 | Project Manager |
May 30, 2023 | HPHC Historical Preservation No Effect |
Sep 22, 2023 | Application Accepted |
Sep 22, 2023 | Permit Approved |
Sep 22, 2023 | Biologist Report |
Sep 22, 2023 | Engineering Report |
Sep 22, 2023 | Typist for Processing |
Sep 22, 2023 | Executive Sign Off |
Sep 22, 2023 | Sent to Photo Copy |
Sep 26, 2023 | Permit Mailed |
Oct 03, 2023 | Land Evidence Date |