Action Date | Action Description |
---|---|
May 12, 2023 | Assent Application Received |
May 17, 2023 | Administrative Review for Completeness |
May 23, 2023 | Eng Team Review for Completeness |
May 23, 2023 | Project Manager |
May 23, 2023 | Application Accepted |
Jun 06, 2023 | HPHC Historical Preservation No Effect |
Sep 13, 2023 | 30 day Public Notice Issued |
Oct 13, 2023 | Public Notice End Date |
Oct 25, 2023 | Engineering Report |
Oct 27, 2023 | Typist for Processing |
Oct 27, 2023 | Executive Sign Off |
Oct 27, 2023 | Sent to Photo Copy |
Oct 27, 2023 | Permit Approved |
Nov 01, 2023 | Permit Mailed |
Oct 11, 2024 | Duplicate Original Assent requested/mailed |
Oct 18, 2024 | Land Evidence Date |