Action Date | Action Description |
---|---|
Jul 26, 2023 | Freshwater Wetlands Application - New - received |
Aug 01, 2023 | Administrative Review for Completeness |
Aug 16, 2023 | Bio Team Review for Completeness |
Aug 16, 2023 | Application Accepted |
Aug 16, 2023 | Project Manager |
Sep 15, 2023 | HPHC Historical Preservation No Effect |
Oct 10, 2023 | Additional Information Received |
Jan 31, 2024 | Biologist Report |
Feb 01, 2024 | Typist for Processing |
Feb 01, 2024 | Executive Sign Off |
Feb 01, 2024 | Sent to Photo Copy |
Feb 01, 2024 | Permit Approved |
Feb 05, 2024 | Permit Mailed |
Feb 28, 2024 | Land Evidence Date |