Action Date | Action Description |
---|---|
Aug 17, 2023 | Assent Application Received |
Aug 23, 2023 | Administrative Review for Completeness |
Sep 11, 2023 | Eng Team Review for Completeness |
Sep 11, 2023 | Deficient Application - Owner Notification Sent |
Dec 04, 2023 | Deficiency Response Received |
Dec 18, 2023 | Eng Team Review for Completeness |
Dec 18, 2023 | Application Accepted |
Dec 18, 2023 | Project Manager |
Jan 02, 2024 | Executive Sign Off |
Jan 02, 2024 | Sent to Photo Copy |
Jan 03, 2024 | HPHC Historical Preservation No Effect |
Jan 08, 2024 | Engineering Report |
Jan 09, 2024 | Typist for Processing |
Jan 09, 2024 | Permit Approved |
Jan 11, 2024 | Permit Mailed |
Feb 01, 2024 | Land Evidence Date |