Action Date | Action Description |
---|---|
Sep 05, 2023 | Assent Application Received |
Sep 12, 2023 | Administrative Review for Completeness |
Sep 18, 2023 | Eng Team Review for Completeness |
Sep 18, 2023 | Application Accepted |
Sep 18, 2023 | Project Manager |
Oct 31, 2023 | HPHC Historical Preservation No Effect |
Nov 06, 2023 | Engineering Report |
Nov 07, 2023 | Typist for Processing |
Nov 07, 2023 | Executive Sign Off |
Nov 07, 2023 | Sent to Photo Copy |
Nov 07, 2023 | Permit Approved |
Nov 10, 2023 | Permit Mailed |
Nov 16, 2023 | Land Evidence Date |