Action Date | Action Description |
---|---|
Sep 25, 2023 | CHA Worksheet received |
Sep 25, 2023 | Assent Application Received |
Sep 28, 2023 | Administrative Review for Completeness |
Oct 02, 2023 | Bio Team Review for Completeness |
Oct 02, 2023 | Project Manager |
Oct 02, 2023 | Application Accepted |
Oct 20, 2023 | Biologist Report |
Oct 31, 2023 | HPHC Historical Preservation No Effect |
Nov 02, 2023 | Typist for Processing |
Nov 02, 2023 | Executive Sign Off |
Nov 02, 2023 | Sent to Photo Copy |
Nov 02, 2023 | Permit Approved |
Nov 06, 2023 | Permit Mailed |
Nov 14, 2023 | Land Evidence Date |
Dec 21, 2023 | Modification Request |
Jan 02, 2024 | Administrative Review for Completeness |
Jan 03, 2024 | Bio Team Review for Completeness |
Jan 03, 2024 | Project Manager |
Jan 03, 2024 | Application Accepted |
Jan 03, 2024 | Biologist Report |
Jan 09, 2024 | Typist for Processing |
Jan 09, 2024 | Executive Sign Off |
Jan 09, 2024 | Sent to Photo Copy |
Jan 09, 2024 | Modification Approved |
Jan 18, 2024 | Land Evidence Date |
Feb 09, 2024 | HPHC Historical Preservation No Effect |