Action Date | Action Description |
---|---|
Oct 03, 2023 | Buffer Zone Management Application Received |
Oct 06, 2023 | Administrative Review for Completeness |
Oct 10, 2023 | Bio Team Review for Completeness |
Oct 10, 2023 | Application Accepted |
Oct 10, 2023 | Project Manager |
Oct 19, 2023 | HPHC Historical Preservation No Effect |
Mar 08, 2024 | Additional Information Received |
Mar 13, 2024 | Category M assigned |
Mar 13, 2024 | Biologist Report |
Mar 18, 2024 | Typist for Processing |
Mar 18, 2024 | Executive Sign Off |
Mar 18, 2024 | Sent to Photo Copy |
Mar 18, 2024 | Permit Approved |
Mar 20, 2024 | Permit Mailed |
Sep 25, 2024 | Commencement of Work Notice received |