Action Date | Action Description |
---|---|
Oct 05, 2023 | Assent Application Received |
Oct 10, 2023 | Administrative Review for Completeness |
Nov 20, 2023 | Additional Information Received |
Nov 22, 2023 | Application Accepted |
Nov 22, 2023 | Project Manager |
Nov 22, 2023 | Eng Team Review for Completeness |
Dec 01, 2023 | HPHC Historical Preservation No Effect |
Dec 18, 2023 | Engineering Report |
Dec 26, 2023 | Typist for Processing |
Dec 26, 2023 | Executive Sign Off |
Dec 26, 2023 | Sent to Photo Copy |
Dec 26, 2023 | Permit Approved |
Dec 28, 2023 | Permit Mailed |
Oct 09, 2024 | Land Evidence Date |