Action Date | Action Description |
---|---|
Oct 05, 2023 | Assent Application Received |
Oct 10, 2023 | Administrative Review for Completeness |
Oct 11, 2023 | Bio Team Review for Completeness |
Oct 11, 2023 | Application Accepted |
Oct 11, 2023 | Project Manager |
Nov 02, 2023 | Biologist Report |
Nov 10, 2023 | HPHC Historical Preservation No Effect |
Nov 16, 2023 | Typist for Processing |
Nov 20, 2023 | Executive Sign Off |
Nov 20, 2023 | Sent to Photo Copy |
Nov 20, 2023 | Permit Mailed |
Nov 20, 2023 | Permit Approved |
Dec 01, 2023 | Land Evidence Date |