Action Date | Action Description |
---|---|
Dec 06, 2023 | CHA Worksheet received |
Dec 06, 2023 | Assent Application Received |
Dec 07, 2023 | Administrative Review for Completeness |
Dec 11, 2023 | Bio Team Review for Completeness |
Dec 11, 2023 | Project Manager |
Dec 11, 2023 | Application Accepted |
Dec 15, 2023 | Additional Information Received |
Jan 05, 2024 | HPHC Historical Preservation No Effect |
Jan 09, 2024 | Note to File |
Jan 10, 2024 | Additional Information Requested from Applicant |
Jan 11, 2024 | Phone Call |
Feb 21, 2024 | Plans Received |
Feb 26, 2024 | Biologist Report |
Feb 27, 2024 | Typist for Processing |
Feb 27, 2024 | Executive Sign Off |
Feb 27, 2024 | Sent to Photo Copy |
Feb 27, 2024 | Permit Approved |
Mar 04, 2024 | Permit Mailed |
Mar 04, 2024 | Plans Received |
Oct 21, 2024 | Land Evidence Date |