Action Date | Action Description |
---|---|
Dec 22, 2023 | Maintenance Certification Request |
Dec 28, 2023 | Administrative Review for Completeness |
Jan 10, 2024 | Eng Team Review for Completeness |
Jan 10, 2024 | Application Accepted |
Jan 10, 2024 | Project Manager |
Feb 21, 2024 | HPHC Historical Preservation No Effect |
Feb 22, 2024 | Plans Received |
Feb 28, 2024 | Engineering Report |
Mar 05, 2024 | Typist for Processing |
Mar 05, 2024 | Executive Sign Off |
Mar 05, 2024 | Sent to Photo Copy |
Mar 05, 2024 | Permit Approved |
Mar 07, 2024 | Permit Mailed |
Mar 20, 2024 | Land Evidence Date |