Action Date | Action Description |
---|---|
Land Evidence Date | |
Dock Post-Construction Certification by Engineer received. | |
Jan 26, 2024 | Assent Application Received |
Feb 01, 2024 | Administrative Review for Completeness |
Feb 12, 2024 | Bio Team Review for Completeness |
Feb 12, 2024 | Project Manager |
Feb 14, 2024 | Application Accepted |
Feb 14, 2024 | Category A* (Docks) |
Feb 16, 2024 | HPHC Historical Preservation No Effect |
Apr 12, 2024 | Additional Information Received |
May 31, 2024 | 30 day Public Notice Issued |
Jun 30, 2024 | Public Notice End Date |
Jul 23, 2024 | Comments Received |
Jul 24, 2024 | Comments Received |
Jul 30, 2024 | Public Notice End Date Extension Granted |
Sep 10, 2024 | Plans Received |
Sep 16, 2024 | Engineering Report |
Sep 16, 2024 | Biologist Report |
Sep 17, 2024 | Typist for Processing |
Sep 17, 2024 | Executive Sign Off |
Sep 17, 2024 | Sent to Photo Copy |
Sep 17, 2024 | Permit Approved |
Sep 19, 2024 | Permit Mailed |