Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Jan 29, 2024 | Assent Application Received |
Feb 02, 2024 | Administrative Review for Completeness |
Feb 05, 2024 | Eng Team Review for Completeness |
Feb 05, 2024 | Application Accepted |
Feb 05, 2024 | Project Manager |
Feb 20, 2024 | HPHC Historical Preservation No Effect |
Mar 04, 2024 | 30 day Public Notice Issued |
Apr 04, 2024 | Public Notice End Date |
May 10, 2024 | Dock/1.1.6 Review approval |
Jun 25, 2024 | Engineering Report |
Jun 28, 2024 | Typist for Processing |
Jun 28, 2024 | Executive Sign Off |
Jun 28, 2024 | Sent to Photo Copy |
Jun 28, 2024 | Permit Approved |
Jul 03, 2024 | Permit Mailed |
Jul 10, 2024 | Land Evidence Date |