Action Date | Action Description |
---|---|
Feb 21, 2024 | Buffer Zone Management Application Received |
Feb 27, 2024 | Administrative Review for Completeness |
Feb 28, 2024 | Bio Team Review for Completeness |
Feb 28, 2024 | Project Manager |
Feb 28, 2024 | Application Accepted |
Apr 05, 2024 | HPHC Historical Preservation No Effect |
Apr 29, 2024 | Additional Information Received |
Jul 09, 2024 | Additional Information Requested from Applicant |
Jul 25, 2024 | Additional Information Requested from Applicant |
Aug 09, 2024 | Additional Information Received |
Sep 10, 2024 | Typist for Processing |
Sep 10, 2024 | Executive Sign Off |
Sep 10, 2024 | Sent to Photo Copy |
Sep 10, 2024 | Permit Approved |
Sep 10, 2024 | Biologist Report |
Sep 16, 2024 | Permit Mailed |
Oct 07, 2024 | Land Evidence Date |