Action Date | Action Description |
---|---|
Feb 29, 2024 | Maintenance Certification Request |
Mar 05, 2024 | Administrative Review for Completeness |
Apr 08, 2024 | Eng Team Review for Completeness |
Apr 08, 2024 | Deficient Application - Owner Notification Sent |
Apr 16, 2024 | Deficient Application Picked Up |
May 20, 2024 | Deficiency Response Received |
Jun 03, 2024 | Project Manager |
Jun 10, 2024 | Eng Team Review for Completeness |
Jun 10, 2024 | Application Accepted |
Jul 03, 2024 | Engineering Report |
Aug 07, 2024 | HPHC Historical Preservation No Effect |
Aug 08, 2024 | Permit Approved |
Aug 08, 2024 | Typist for Processing |
Aug 08, 2024 | Executive Sign Off |
Aug 08, 2024 | Sent to Photo Copy |
Aug 09, 2024 | Permit Mailed |
Aug 26, 2024 | Land Evidence Date |