Action Date | Action Description |
---|---|
Assent Requirement | |
Apr 01, 2024 | Assent Application Received |
Apr 01, 2024 | CHA Worksheet received |
Apr 04, 2024 | Administrative Review for Completeness |
Apr 17, 2024 | Bio Team Review for Completeness |
Apr 17, 2024 | Application Accepted |
Apr 17, 2024 | Project Manager |
May 13, 2024 | Plans Received |
May 20, 2024 | HPHC Historical Preservation No Effect |
Jun 05, 2024 | Additional Information Requested from Applicant |
Jun 18, 2024 | Plans Received |
Jun 24, 2024 | Biologist Report |
Jun 27, 2024 | Typist for Processing |
Jun 27, 2024 | Executive Sign Off |
Jun 27, 2024 | Sent to Photo Copy |
Jun 27, 2024 | Permit Approved |
Jul 03, 2024 | Permit Mailed |
Jul 11, 2024 | Assent Correction Mailed |
Jul 24, 2024 | Land Evidence Date |